North End History

BRIEF NORTH END REDEVELOPMENT HISTORY

2006 – NE declared area in need of redevelopment 

2008 – NE Plan approved

  • developer CMA and Wave
  • up to 80 room hotel up to 65 ft high
  • up to 80 condos up to 48 ft high
  • up to 85 residences
  • underground parking up to 3.5ft above ground

2011 – OGHOA NE committee drafts Construction Priorities document

  • itemized transparency, preconstruction traffic study, order of construction, just in time deliveries only during business hours, design to decrease density
  • approved by membership and presented to the NTC and is still relevant 

NE Delay – law suit, Sandy, boardwalk repair, developer finance

September 9 2019 – NE Agreement approved by NTC

  • Developer — MB@ and Wave = OGNED
  • 40 room hotel with no conference space
  • 39 condos (37 – 2 bedroom, 2 – 3 bedroom)
  • 10 houses on Spray
  • Retail on Boardwalk
  • 140 underground spaces on one level

February 2020 – Planning board conditionally approved NE Agreement

  • Need CAFRA approval from NJ DEP
  • Need HPC approval
  • Fire safety review

March 2021 – OGNED obtains NJDEP CAFRA approval  (exp 3/2026)

June 2022 – HPC denies OGNED HPC Approval for NE

  • October 2022 – HPC memorializes the HPC Decision document
  • OGNED sues Neptune Township because it allegedly did not decide OGNED’s application within the legal time period
  • Neptune Township filed motion to dismiss the lawsuit
  • Court date for summary judgement repeatedly postponed

November 2022 – NTC announces a vote on a settlement with OGNED and an Amended NE Agreement that basically allows the NE to move forward without HPC approval

April 2023 – NTC voted to pass the NE Ordinance

September 2024 – Amended NE Site Plan is on the Planning Board Agenda

  • At the last minute OGNED pulls out of the Planning Board meeting
  • 2 private citizens had hired a lawyer, land use lawyer and architect. Their lawyer had found that there are 2 family homes that are outside the single-family zone